AC Hotel Named CFA 2026 Above Grade Structure Project of the Year

2026In Our WorkBy Custom Concrete

At Custom Concrete, we take pride in delivering projects that push the boundaries of craftsmanship, coordination, and technical excellence. That's why we're honored to celebrate the AC Hotel project being recognized by the Concrete Foundations Association (CFA) as the 2026 Above Grade Structure Project of the Year.

This award is a testament to the dedication of the entire project team and the strong partnerships that made it possible. We are proud to collaborate with Holladay Construction Group and Thompson Thrift to bring this impressive hospitality development to life.

Building an Award-Winning Structure

Spanning nearly 52,000 square feet, the AC Hotel project required extensive planning, coordination, and execution from the ground up. The project incorporated more than 3,040 cubic yards of concrete and approximately 376,000 pounds of reinforced steel, creating the structural backbone needed to support the development.

What made the project especially unique was its complexity. The foundation system included five custom-shaped mat foundations, dozens of large column pads, continuous perimeter footings, and nearly 2,500 tons of backfill material. From the earliest stages of construction, every element required precise sequencing and coordination to maintain schedule and quality.

Logistical Challenges

The project featured a variety of structural elements, including foundation walls, reinforced concrete columns, and massive shear walls reaching heights of more than 26 feet tall. These walls required sophisticated, engineered formwork systems, crane-assisted installation, and the placement of more than 100 embedded components.

As the project progressed, the team navigated a large open excavation, tight site logistics, and a demanding construction schedule. Multiple crews worked simultaneously through different phases of the project, ensuring that foundation work, vertical construction, and backfilling activities remained on track.

The complexity only increased as winter approached. Extreme cold temperatures, high winds, and heavy snowfall threatened to impact progress. Through extensive planning, cold-weather practices, and a commitment from field crews, the team successfully recovered nearly 25 days of lost production and maintained the project schedule.

The Power of Partnership

Success on a project of this scale doesn't happen without collaboration. Early coordination between the project team, engineers, inspectors, trade partners, and leadership was critical.

The site itself added another layer of complexity, as the AC Hotel shared access with other active commercial developments on the property. Throughout construction, teams coordinated approximately 60 semi-truck deliveries, 150 stone deliveries, and 55 concrete placements while maintaining safe and efficient operations.

These efforts reflect the teamwork, communication, and problem-solving that are essential to delivering successful projects.

A Recognition of Excellence

The CFA's Above Grade Structure Project of the Year award recognizes outstanding achievement in concrete construction, and the AC Hotel project exemplifies the level of planning, innovation, and craftsmanship required to earn that distinction.

Thanks to the Concrete Foundations Association for this incredible honor and extend our congratulations to everyone who contributed to the success of the AC Hotel project. We are proud of what was accomplished and look forward to continuing to build projects that leave a lasting impact on the communities we serve.